HPR Shades of Green Construction Status

Column reinforcement rising from footings at the HPR Shades of Green site, photographed 16 August 2026


HPR Shades of Green is currently in its early sub-structure phase, and site clearance, earthwork, and foundation footing are underway. Boundary fencing is complete, and a scale model of the 4 BHK villa is on display at the on-site sales office. Full villa construction and amenities will begin from 10th Aug, 2026 onwards.

What Is Already Built


Based on the current site progress, these elements are complete or actively coming up:

  • Site clearance and ground levelling across the 4.50-acre plot
  • Boundary wall and perimeter fencing work
  • A scale model of the 4 BHK villa on display at the on-site sales office, giving buyers an early look at the final design
  • Early landscaping around the sales office zone

HPR Shades of Green Construction Status in Photos


Every photograph below is GPS-stamped at Kadusoppanahalli Village on the Kannuru - Bagaluru Road, Bengaluru, and can be checked against the project coordinates filed with K-RERA. They run in date order from the levelled ground of June 2026 through to the foundation and column work under way in August 2026.

Levelled 4.50-acre land at HPR Shades of Green with perimeter wall and neighbouring residences, Kadusoppanahalli, Bengaluru

Full width of the 4.50-acre parcel after levelling, with the perimeter wall in place — 17 June 2026

Graded ground and site office cabin at HPR Shades of Green villa project, Kannuru - Bagaluru Road, North Bangalore

Graded ground with the site office cabin set up along the far boundary — 17 June 2026

Completed brick compound wall along the boundary of the HPR Shades of Green 83-villa site, Kadusoppanahalli

Brick compound wall completed along the site boundary, with the sales cabin in the background — 13 July 2026

Cleared and compacted ground at HPR Shades of Green ready for foundation work, Bidarahalli Hobli, Bengaluru East

Cleared and compacted ground ahead of the 01 August 2026 foundation start — 13 July 2026

Column reinforcement rising from footings at HPR Shades of Green, 83-villa project on Kannuru - Bagaluru Road, North Bangalore

Foundation and column reinforcement in progress across the site — 16 August 2026

Wide view of the 4.50-acre HPR Shades of Green site with column steel and site cabins, Kannuru - Bagaluru Road, Bengaluru

Wide view of the 4.50-acre parcel with column steel in place and site cabins along the boundary — 16 August 2026

Site Walk-through Video — 16 August 2026

A short walk-through filmed on site on 16 August 2026, panning across the footings and column reinforcement now in place. Like the photographs above, it is GPS-stamped at Kadusoppanahalli Village on the Kannuru - Bagaluru Road.

Walk-through across the site showing foundation and column reinforcement — 16 August 2026

What Will Begin Shortly


These major works are scheduled to start in the coming months, as construction moves past the foundation stage:

  • Super-structure work for all 83 villas, including RCC framing and masonry
  • Internal roads connecting each villa block
  • Clubhouse and amenity construction, including the pool and sports zone
  • Doors, windows, and basic electrical and plumbing work

Construction Timeline: Start to Finish


  • Start date: 1 August 2026, when the earthwork and site levelling started.
  • Sub-structure completion: Expected by August 2027, covering the foundation and the plinth work.
  • Super-structure completion: Expected by mid-2029, covering the villa framing, plastering, and the fittings.
  • Final finishing: Runs from mid-2030 to July 2031, covering the landscaping and the elevation work.
  • End date: 31 July 2031, marking the construction completion.

RERA-Approved Project Schedule


This table summarises the official construction phases filed with the Karnataka RERA board.

Sub Structure

Sub-Structure Activity Start Date End Date
Sub-Structure Earthwork and levelling 01-08-2026 28-01-2027
Sub-Structure Foundation footing work 06-08-2026 07-08-2027
Sub-Structure Up to plinth level 11-08-2026 12-08-2027
Sub-Structure Sub-structure flooring 11-08-2026 12-08-2027

What Is Sub-Structure Work?

Sub-structure work covers everything built below ground level. This includes earthwork, foundation footings, and flooring up to the plinth level.

Super Structure

Category Activity Start Date End Date
Super-Structure RCC or MS framed structure 18-08-2026 19-08-2028
Super-Structure Masonry construction 16-11-2026 19-03-2029
Super-Structure Plastering (inside, outside, ceiling) 14-02-2027 17-06-2029
Super-Structure Doors, windows, ventilators 09-02-2028 12-06-2030
Super-Structure Water supply, sanitary, electrification (basic) 09-02-2028 12-06-2030
Super-Structure Dadoing, skirting, flooring, tiles 13-08-2027 14-12-2029
Super-Structure Railing and grill fixing 15-05-2027 15-05-2029

What Is Super-Structure Work?

Super-structure work covers everything above the plinth level. This includes the RCC or MS frame, masonry, plastering, and fitting doors and windows.

Finishing Work

Category Activity Start Date End Date
Finishing Electrification, water supply, sanitary finishing 07-08-2028 09-12-2030
Finishing Painting 13-08-2027 14-12-2029
Finishing Weatherproof work (tile, concrete) 15-05-2027 15-09-2029
Finishing Elevation work 13-08-2027 14-12-2029
Finishing Internal and external work, landscaping 12-06-2030 31-07-2031

What Are Finishing Works?

Finishing works are the final touches applied once the structure is ready. This includes painting, tiling, weatherproofing, and landscaping before handover.

FAQs


1. What is the current status of construction at HPR Shades of Green?

The project is still working on the basics and is doing earthwork

2. Has construction of the villas started at HPR Shades of Green?

They have not started building the villas at HPR Shades of Green. They will start working on the villas after they finish the work.

3. When will HPR Shades of Green be fully built?

HPR Shades of Green is expected to be finished by 31 July 2031.

4. Are they building the clubhouse and other amenities at HPR Shades of Green?

The clubhouse and other amenities at HPR Shades of Green will be built at the same time as the villas.

5. Does RERA check the construction schedule of HPR Shades of Green?

Yes, RERA checks the schedule of HPR Shades of Green. You can see the schedule on the Karnataka RERA website.

6. What is the difference between the work and the work above the ground at HPR Shades of Green?

The basic work is what you do not see; it is below the ground. The work above the ground includes the walls and the frame of the building at HPR Shades of Green.